In line A, municipalities with more than 5,000 inhabitants can participate, even in association with neighboring local authorities, for a maximum contribution of 750,000 with a minimum co-participation of 10% or for a maximum contribution of 1.5 million euros with a minimum co-participation of 15%.
The tender rewards those who increase participation up to 20 percentage points, by presenting projects for multidisciplinary facilities that carry out 2 to 4 CONI sports at a competitive level, one of which is classified as CIP, in compliance with environmental regulations, the reduction of energy consumption and those equipped with a good management plan that provides for social inclusion.
It is necessary to reach a minimum score threshold based also on territorial indicators which favor municipalities with young inhabitants (from 15 to 24 years), with economic hardship (under 15 thousand income), Crime (reported thefts and robberies) and School dropouts (early exit from the system between the ages of 18 and 24) above the national average with a significant score of over 40 points overall.
Please note: our advice is to check whether you exceed the 55 minimum points by a certain margin and hurry to submit your application no later than the first few hours of opening.
Line A provides for the recovery and/or completion and/or adaptation of existing sports facilities, with a focus on competitive activities through safety measures, the removal of architectural barriers and energy efficiency.
It is aimed at Municipalities with a populationover 5,000 inhabitants or Municipalities with a population equal to or less than 5,000 inhabitants, but capable of reaching the threshold of 5,000 inhabitants through an agreement with other neighboring local authorities.
It is possible to submit only one application provided that they have not already directly benefited from contributions assigned under the Sport and Suburbs public notices, relating to the years 2020, 2022, 2023 and 2024, unless the financed intervention has been fully implemented.
The submission of applications is at the counter with opening scheduled from 12:00 on 5 May 2025 to 12:00 on 16 June 2025.
For any requests for clarification, you must write to: sporteperiferie@governo.it, no later than, under penalty of inadmissibility, 12:00 on 6 June 2025.
It is also possible to add other sources of funding, both national and local, for example through ICSC and GSE to the maximum extent of sharing, pursuant to article 2 paragraph 4 of the regulations. If the GSE incentives exceed this sum, the sums available will be reduced by the Department or can be reinvested in the same intervention for improvements.
The proposals will be admitted to financing in order of arrival upon reaching the threshold score of 55 points up to the amount of available resources equal to 65 million. It is understood that proposals that do not reach the threshold score will be considered excluded.
Multidisciplinary facilities will have a score based on the number of sports disciplines that can be practiced after the intervention as follows:
The sports disciplines that can be practiced in the facility among those recognized by CONI and CIP with CONI Resolution no. 1691 of 07.07.202, the competitive practice of the latter must be certified through the transmission of specific documents that reveal the actual registration for the holding of tournaments, championships etc.;
In our opinion, based on previous experience, it is necessary that amateur sports associations, regularly registered for the carrying out of competitive activities, even outside the municipal territory, have expressed an interest in using the sports infrastructure covered by the works, even for the sole purpose of training.
For example, an 11-a-side football pitch made of natural grass can withstand a limited number of hours of play, while a POWERgrass hybrid grass pitch can be used up to 30 hours a week with reduced maintenance and has no fixed playing lines because the natural grass is dominant, thus allowing more sports to be played by changing the playing lines every weekend and even during the week. As the grass grows, it "blows out" the previous lines and with the help of effective markers the field can be marked in less than an hour.
We propose the sports disciplines that we believe also satisfy the next point D, involving the most fragile part of the population:
Below, we list some also referring to the Paralympic sports that can be played on the grass or occupying modest spaces around the main field:
Our technicians can assist your designer in developing an executive project for the hybrid grass field, fences and lighting and photovoltaic systems with or without storage. For more in-depth information, we recommend consulting the design guidelines at the following link: Design (powergrass.it).
The design level should not be confused with design approval, the act of verifying and validating the design. The design level and the related score are defined by the documents produced according to the new procurement code and by the consistency of the documents with each other. For example, the Bill of Quantities must report the works foreseen in the report. The drawings must show the measurements of the Bill of Quantities. Body voices must be avoided because they are misleading and generate controversy. The timetable is not a colored diagram, the sequence of works must be indicated to avoid interference and the times must be consistent with the human resources made available and the estimated labor costs.
The verification of the project takes on the value of an asseveration of the project because the technician in charge does not go into the merits of the design choices but of the possibility of carrying out the work, and therefore ascertains the presence of all the necessary investigations and authorizations from the competent bodies. For example, the geological verification, the analysis of the excavation soil, the availability of recovery plants or landfills in the area, the availability of quarries for the extraction of materials near the construction site, as well as the various necessary opinions of the competent bodies such as the opinion of CONI.
In conclusion, after a comparison with the RUP of the tender, an executive project can be presented, reserving the right to produce opinions at a later stage, after having verified the project, thus avoiding committing an "irregular" act in the rush to complete everything.